A Resourceful Titan Success

By Administrator Titan Machinery built its Shared Resource Center (SRC) in West Fargo, N.D., to centralize back office functions performed for each of the company’s 91 dealership locations in eight states. The new facility provides space for the company headquarters with areas for accounting, information technology, marketing, training, multipurpose cafeteria with kitchen, and a limited… Continue reading A Resourceful Titan Success
By Administrator

Titan Machinery built its Shared Resource Center (SRC) in West Fargo, N.D., to centralize back office functions performed for each of the company’s 91 dealership locations in eight states. The new facility provides space for the company headquarters with areas for accounting, information technology, marketing, training, multipurpose cafeteria with kitchen, and a limited amount of warehouse space for critical parts that normally require long lead time from a factory. Providing centralized support for a network of dealerships in Iowa, Minnesota, Wisconsin, North Dakota, South Dakota, Nebraska, Montana and Wyoming, Titan sells and services CaseIH, Case Construction, New Holland and New Holland Construction brands, along with some short-line equipment and consumer products.

Titan has built multiple dealership facilities in local markets using pre-engineered metal building systems. The company’s favorable experience with them-particularly the weathertightness of the Kansas City, Mo.-based Butler Manufacturing’s MR-24 standing seam metal roof system-made Titan facility executives choose the same materials solution for the much larger center.

A pre-engineered metal building structure was used for the training shop and warehouse spaces. The overall structure incorporates a structural post and- beam style for the underground parking and the second floor framing of the corporate office space.TitianSRC_8016

A hybrid is necessary

Achieving the maximum spans and minimizing the number of columns desired by the owner, while using concrete floors was the center’s biggest challenges. Because of this, the facility required a hybrid building comprised of a combination of metal building systems, conventional steel framing and other materials. A hybrid design allowed Titan to achieve the functionality of the facility as well as the aesthetic appearance designed to create their brand. The structural steel rigid frames, second floor beams, metal roof deck and roof purlins are all Butler Manufacturing products.

The structural steel supplied by Butler is a rigid frame system with X-bracing in the transverse direction. “Typically Butler manufacturing has a standard pre-engineered building product that doesn’t have as much flexibility when you get to a complex building,” says Robert Thompson, construction manager at C.I. Construction, Alexandria, Minn., a Butler builder. “This building was complex in that we had continuous windows all the way around. We had pre-cast floors, a parking garage underneath. The use of both pre-engineered metal beams for spans kept the structure light weight. Mill steel pieces were used for floor support and columns, where we needed much greater structural strength.The B-loading for the windows was structural mill tubing. This allowed us to have a very low deflection in the sidewalls to accommodate the use of continuous windows all the way around the building.”

Hybrid elements include the second floor precast concrete core floor bearing on Butler steel beams. The main floor is precast concrete core floor bearing on precast concrete inverted T beams and is supported on cast-in-place concrete columns with integral corbels. It carries the horizontal rigid frame column reactions in tension. Loading dock levelers were integrated into the precast core floor system. Common metal building components include purlins, “C” girts, bracing, mill products and a unique roof system. “The roof is seamed like the top of a Coke can,” Thompson says. “It’s called a Pittsburgh 360 degree double-lock roll seam and we believe in the high life cycle of this roof. We can install a roof like this with high energy efficiency with the spacer blocks for thermal penetration of cold air. It allows for very thick layers of fiberglass insulation to be laid between the bottom of the roof and the roof panel. We typically see this roof perform for at least 20 years with little if any maintenance. It’s a low-cost, low-maintenance product.” The roof’s UL-90 wind uplift rating protects the building against Fargo’s high winds.TitianSRC_7402

Metal and the exterior wall

The exterior wall construction consists of Chesapeake, Va.-based Mitsubishi Plastics Composites America Inc.’s ALPOLIC aluminum composite panels fabricated by Metal Design Systems, a Koreteck panelized insulating wall system from Acsys Inc., Hayden, Idaho, steel studs and Butler factory-insulated metal wall panels. Butler columns provide support with steel tube lintels incorporated for long runs of Chicago-based CRL U.S. Aluminum series 2200 exterior ribbon windows. The R-48 roof and R-40 wall insulation values complement the energy-efficient HVAC.

The metal wall panels give the building very clean lines and a contemporary appearance. “Two different types of panels were utilized: one at the office areas, and another at the shop and warehouse spaces,” says Kevin Bartram, AIA, president, Mutchler Bartram Architects PC, Fargo, N.D. “The two panel types work together in color and detailing and add interest to the overall massing. The wall covering on the warehouse area and the rear of the building is Butler’s TextureWall system. This TextureWall system has factory installed 4-inch foam that has an R-value of 32. The metal structure provided large spatial volumes with very few columns and obstructions allowing a great deal of flexibility with the interior layout and any future reconfigurations of the interior spaces.

The metal panels can be removed and re-installed when the building is expanded, and new panels added where necessary with a certainty that colors and detailing will match.” The ALPOLIC ACM panels benefit the Shared Resource Center’s exterior cladding by providing the rigidity of heavy-gauge sheet metal in a lightweight composite material. They aid in vibration dampening, durability and ease of maintenance. The ACM panels were produced by continuously bonding two thin sheets of aluminum on both sides of a PVC core. “They gave the building a sleek appearance with nice crisp corners and no ‘oil canning,'” Thompson says. Bartram believes using a pre-engineered metal structure and different types of metal panels has provided a unified design and image for all of the Titan facilities with easy expansion planned into the structure. Titan is already planning to expand this facility in 2012-13.progress photos 192 Framing best

 

[sidebar]

Staying energy efficient

The center’s variable refrigerant volume (VRV) system is similar to heat pump systems. “The system harvests the heat from internal loads such as computers, lights, and people in order to heat the rooms at the perimeter of the building,” says Kathy Nordness, PE, LEED AP BD+C, mechanical engineer, MBN Engineering Inc., Fargo, N.D. “Heat pumps share the diversity of the building load in the water piping. The VRV system shares the diversity in the refrigerant piping, therefore reducing the compressor energy required to heat and cool the building. The VRV system at Titan SRC has efficiency similar to buildings with geothermal heat pumps, but the cost of the system is about 30 percent lower. The annual energy consumption is less than 60 kbtu/sf. The target for energy-efficient buildings is normally about 80 kbtu/sf. Commonly, commercial buildings are higher than 100 kbtu/sf.”

 

[sidebar]

Software coordinates construction

Constructing the shared resource center required a lot of subcontractors and material suppliers, especially since C.I. Construction doesn’t self-perform anything. Software eased this process. “We have integrated construction software called Construction Project Manager (CPM),” says Robert Thompson, construction manager at C.I. Construction, Alexandria, Minn., a Butler builder. “It ties together everything from contracts to requests for proposals to change orders to submittals where we can track it and it tells us when we need to be recontacting someone for lack of response, it allows us to track all the subcontracts and change orders as it relates to pay requests using standard AIA documentation for pay requests of the owners. It ties all the correspondence and construction documentation together. We use Revit internally, which allows us to use BIM files. We can overlay at 2-D lines. One of our suppliers uses 3-D drafting and so we can overlay their products into our plans with conflict in points. We are using it more and more to solve conflicts, and schedule better with less rework. We use Microsoft Project to schedule the project and demonstrate critical paths.”

 

[sidebar]

Titan Machinery’s Shared Resource Center, West Fargo, N.D.

Building owner: Titan Machinery Inc., West Fargo

Architect: MBA Architects, Fargo, N.D.

Construction Manager: C.I. Construction LLC, Alexandria, Minn.

Structural engineer: Solien & Larson Engineers PC, Fargo

Mechanical engineer: MBN Engineering Inc., Fargo

Soil engineer: Northern Technologies Inc., Fargo

Erector: Gateway Building Systems Inc., Fargo

ACM panel fabricator: Metal Design Systems Inc., Cedar Rapids, Iowa

ACM panel installer: Hebo Construction LLC, Alexandria

Precast concrete supplier: Molin Concrete, Circle Pines, Minn.

Aluminum composite material: Mitsubishi Plastics Composites America Inc., Chesapeake, Va., www.alpolic-usa.com, Circle #35

Insulated panel system: Acsys Inc., Hayden, Idaho, www.acsys.net, Circle #36

Metal building, roof and wall panels: Butler Manufacturing Co., Kansas City, Mo., www.butlermfg.com, Circle
#37

Windows: CRL U.S. Aluminum, Chicago, www.usalum.com, Circle #38

 

[sidebar]

Titan Shared Resource Center Timeline

Groundbreaking: May 11, 2009 Foundation footings, walls and piers started: May 25, 2009

Structural steel delivery: July 13, 2009

Precast beams and planks installed for underground parking roof and first floor: July 20, 2009

Steel erection started: July 27, 2009

Poured first floor topping: August 17, 2009

Installed second floor precast: October 1, 2009

Poured basement with in-floor electric heat panels: October 19, 2009

Installed Butler TextureWall and Koreteck insulated panel system: November 2, 2009

Started interior wall framing: November 16, 2009

Installed exterior brick: November 26, 2009

Started ACM panel installation: December 8, 2009

Building completely enclosed: December 15, 2009

Started interior finishes: February 10, 2010

Temporary occupancy granted: May 9, 2010

Owner move-in started: May 9, 2010

Final occupancy and completed: May 15, 2010